Hubble Space Telescope payload computer , NSSC-1

Hubble Space Telescope payload computer that halted on June 13, 2021 

NASA continues to work to resolve a problem with the Hubble Space Telescope payload computer that halted on June 13. After performing tests on several of the computer's memory modules, the results indicate that a different piece of computer hardware may have caused the problem, with the memory errors being only a symptom. The operations team is investigating whether the Standard Interface (STINT) hardware, which bridges communications between the computer’s Central Processing Module (CPM) and other components, or the CPM itself is responsible for the issue. The team is currently designing tests that will be run in the next few days to attempt to further isolate the problem and identify a potential solution.  

background info:




 

safe mode:

In May 2009, STS-125 was launched and the astronauts installed the existing unit. The replacement contains original hardware from the 1980s with four independent 64K memory modules of Complementary Metal-Oxide Semiconductor (CMOS) memory. Only one memory module is used operationally, with the other three serving as backups. All four modules can be used and accessed from either of the redundant payload computers. 

25 June 2021

Additional tests performed on June 23 and 24 included turning on the backup computer for the first time in space. The tests showed that numerous combinations of these hardware pieces from both the primary and backup payload computer all experienced the same error — commands to write into or read from memory were not successful.

Since it is highly unlikely that all individual hardware elements have a problem, the team is now looking at other hardware as the possible culprit, including the Command Unit/Science Data Formatter (CU/SDF), another module on the SI C&DH. The CU formats and sends commands and data to specific destinations, including the science instruments. The SDF formats the science data from the science instruments for transmission to the ground. The team is also looking at the power regulator to see if possibly the voltages being supplied to hardware are not what they should be. A power regulator ensures a steady constant voltage supply. If the voltage is out of limits, it could cause the problems observed.

Over the next week, the team will continue to assess hardware on the SI C&DH unit to identify if something else may be causing the problem. If the team determines the CU/SDF or the power regulator is the likely cause, they will recommend switching to the backup CU/SDF module and the backup power regulator.

14 July,

A series of multi-day tests, which included attempts to restart and reconfigure the computer and the backup computer, were not successful, but the information gathered from those activities has led the Hubble team to determine that the possible cause of the problem is in the Power Control Unit (PCU).


The switch will begin Thursday, July 15, and, if successful, it will take several days to completely return the observatory to normal science operations.


 

 hubblesite


留言

這個網誌中的熱門文章

CMOS sensor trends and astrophotography, from amateur astronomers perspective

Nowadays, even in low light conditions, digital camera can quality pictures with higher ISO, noise and hot pixels have been gradually reduced. Sony has introduced back illumination process for consumer market. Sony BSI sensors evolved  from Exmor to now Exmor RS( stacked) technology. This stacked technology allows further chip size reduction, which has strong demands in smartphone camera market. Digital astrophotography is also benefited from such advances, utilising Back Side Illumination technology Exmor: Within the CMOS sensor, it outputs low-noise digital signals by "on-chip column AD conversion" and "dual noise reduction" to suppress noise in the first half of the process In low light conditions, when a wide aperture is desirable to collect as much light as possible. At apertures wider than f/2.0, back-illuminated Exmor R sensors are significantly more efficient at collecting light than conventional, front-illuminated sensor...

Scythians 斯泰基 塞種 西古提人

900 BC - 200 AD British museum   Tomb of scythe prince, Buktarma valley, 1200 masl, Google map Herodotus   絲路上的帝國 Biblegeography   哥羅西書 3:11  在此並不分希利尼人、猶太人、受割禮的、未受割禮的、化外人、 西古提人 、為奴的、自主的.惟有基督是包括一切、又住在各人之內。 塞種 塞迦  saka 史記漢書 西域傳: 塞種  ctext 昔匈奴破大月氏,大月氏西君大夏,而塞王南君罽賓。塞種分散,往往為數國。自疏勒以西北,休循、捐毒之屬,皆故 塞種 也。 匈奴列傳 Ctext :塞王 《史記》在《大宛列傳》與《匈奴列傳》中, 詳細 記錄了中亞至天山一帶的塞種(塞王、塞地)狀況。例如,文中記載了月氏西破走塞王,導致塞人南遷越過懸度(今帕米爾高原及克什米爾一帶) Baike Genetic history   Genetics  Nih griffin  ? Scytho-Siberian  world 塞迦 saka  wiki Disappeared? Sarmatians ( 薩爾馬泰 , 奄蔡 史記 ,  Aorsi )and goths YouTube  

ultrafast rendezvous to ISS

    14 Oct 2020,  being the first to use a new “ultrafast” rendezvous” scheme with the ISS. Following a flawless ascent to the correct orbit, Soyuz 2 .1a , Soyuz MS-17 caught up with the orbiting laboratory in only two orbits (three hours), halving the time it takes for crew to get to the Station.   The three space travelers of the Soyuz MS-17 mission launched on a six-month mission the International Space Station.  previous 3/4 orbit rendezvous: Soyuz MS-16 4 orbit rendezvous A three-orbit profile was deemed possible without major flight design changes after inauguration of the Soyuz 2-1A rocket that provides a much higher orbit injection accuracy than its predecessors and would allow the two correction maneuvers on Orbit #2 to be eliminated while the Automated Rendezvous Phase would still remain untouched. The deletion of the Orbit #2 maneuvers was expected to slightly tighten the already restrictive phase angle window from and upper limit of 30-35° to 25-28°...